Grolsch Brewery Complex, Boekelo

Specifications - Grolsch Brewery Complex, Boekelo, Netherlands


Key Data
Order year1998
Construction startedEarly 2002
Project typeNew brewery
LocationBoekelo, Holland
Estimated investment€277m
Production3.2 million hectolitres per year (2004) rising to 4 million in 2005 but up to 6 million per year with further expansion
CompletionProduction started end of 2003, April 2004 officially opened, but fully complete early 2005
Key Players
SponsorsGrolsch
ArchitectAndreas Helstedt, HMT
Lead contractorsDanbrew, Sig Simonazzi, Paroc, SI-Tech B.V
Other contractorsBrabant van Opstal, Huppmann, GEA Tuchenhagen, Filtrox, Briggs, Paques, ProLeiT AG, Danfoss, Siemens PLC, Krohne, Aquacare, York Refrigeration, Swisslog
FinancingGrolsch
Featured Suppliers
FILTROX - Filtration Systems and Media
Siemens - Process Instrumentation and Analytics


client logon
Home
Products & Services
Company A-Z
White Papers
Jobs & Careers
Press Releases
Advertise With Us
Events & Exhibitions
Newsletter
New On This Site
About Us
Atom FeedRSS Feed
What is RSS?